Addis Ababa again fills reservoir for its huge dam on Blue Nile river, announces PM Abiy –– a process that continues to irk downstream neighbours Egypt and Sudan.
Ethiopia has completed the third filling of its mega-dam on the Blue Nile, a new milestone that could raise further tensions with downstream neighbours Egypt and Sudan.
The development comes a day after Ethiopia said it had launched electricity production from the second turbine at the Grand Ethiopian Renaissance Dam (GERD) in the northwest of the country.
"Today as you see behind me, the third filling is complete," Prime Minister Abiy Ahmed said from the dam site in images broadcast on state television on Friday.
"The Nile is a gift of God given to us for Ethiopians to make use of it."
There is still no agreement between Ethiopia and its downstream neighbours Egypt and Sudan about the GERD's operations despite talks held under the auspices of the African Union.
Cairo and Khartoum view it as a threat because of their dependence on Nile waters.
But Ethiopia deems it essential for the electrification and development of Africa's second most populous nation.
Abiy assures Egypt and Sudan
There was no immediate reaction from Egypt or Sudan about Friday's development.
But Egypt, an arid nation that relies on the Nile for about 97 percent of its irrigation and drinking water, last month protested to the UN Security Council that the third filling was under way.
Abiy nevertheless sought to reassure Egypt and Sudan over the impact of the dam.
"When we set out to build a dam on the Nile, we said from the beginning that we did not want to make the river our own," he said on Twitter.
"We hope that just like Ethiopia, the other gifted nations of the Nile, Sudan and Egypt, will get to utilise their share."
On Thursday, he had called for negotiations to reach an understanding on the dam but insisted the third filling was not causing any water shortages downstream.
The process of filling the GERD's vast reservoir began in 2020 and it now contains 22 billion cubic metres of water out of a total capacity of 74 billion.
"Compared to last year, we have reached 600 metres which is 25 metres higher than the previous filling," Abiy said.
Project almost complete
Ethiopia first began generating electricity from the GERD in February.
Currently, the two operational turbines, out of a total of 13, have a capacity to generate 750 megawatts of electricity.
It is ultimately expected to produce more than 5,000 megawatts, more than doubling Ethiopia's current output.
Project manager Kifle Horo said on Thursday that overall the dam was now more than 83 percent complete and that the goal was for it to be finished in the next two and a half years.
The structure is 145-metres high and 1.8 kilometres long, straddling the Nile tributary in the Benishangul-Gumuz region of northwestern Ethiopia, not far from the border with Sudan.
Social media is bold.
Social media is young.
Social media raises questions.
Social media is not satisfied with an answer.
Social media looks at the big picture.
Social media is interested in every detail.
social media is curious.
Social media is free.
Social media is irreplaceable.
But never irrelevant.
Social media is you.
(With input from news agency language)
If you like this story, share it with a friend!
We are a non-profit organization. Help us financially to keep our journalism free from government and corporate pressure
0 Comments